None to report
We have no gas supply at our offices and we do not operate company-owned vehicles.
Living Plus Care Services Limited is committed to achieving net zero emissions by 2045, 5 years ahead of the 2050 national target. This plan sets out our emissions, our targets and the actions we are taking across all of our UK operations.

Net zero target5 years ahead of the 2050 national target
At a glance
All figures are in tonnes of carbon dioxide equivalent (tCO2e) and cover our financial years to 30 September.
Baseline 2024/25
19.20
tCO2e, our reference point
Oct 2024 to Sep 2025Current 2025/26
18.10
tCO2e this reporting year
5.7% below baselineTarget 2030/31
13.44
tCO2e, our five-year target
30% below baselineNet zero
2045
Covering all of our UK operations
5 years ahead of the national targetReaching 13.44 tCO2e means cutting 5.76 tCO2e from our baseline. By 2025/26 we had cut 1.10 tCO2e.
Living Plus Care Services Limited is committed to achieving net zero emissions by 2045.
This commitment covers all of our UK operations. We have chosen 2045, 5 years ahead of the 2050 national target, because it matches the NHS target for the emissions it can influence, which include those of the care providers it commissions.
We are a homecare provider based in Hatfield, Hertfordshire, with a second office in Peterborough. Our care workers support people in their own homes.
Travel between visits is the part of our footprint we can most directly reduce, and this plan focuses on it first.
Care delivered in people’s own homesBaseline emissions are a record of the greenhouse gases that have been produced in the past and were produced prior to the introduction of any strategies to reduce emissions. Baseline emissions are the reference point against which emissions reduction can be measured.
Baseline year: 2024/25 (1 October 2024 to 30 September 2025, our financial year)
Most of our footprint is staff travel between care visits, which is part of delivering care in people’s own homes.
We have no gas supply at our offices and we do not operate company-owned vehicles.
The electricity used at our offices in Hatfield and Peterborough, reported on the location-based method.
Staff travel between care visits, other business travel, staff commuting, office waste, purchased goods and services, and our other operational activities.
About 94% of our 2025/26 footprint
Our baseline year is 2024/25. We use the operational control approach. The footprint covers all of our UK operations: our offices at 32 Market Place, Hatfield, AL10 0LN, and Stuart House, Peterborough, PE1 5DD, and the care we deliver from them.
Our figures were calculated from our own records of staff travel and office electricity, using the UK Government GHG Conversion Factors for Company Reporting for each year. Our 2024/25 and 2025/26 figures cover our financial years to 30 September.
| Emissions | Total (tCO2e) |
|---|---|
| Scope 1 | 0.00 |
| Scope 2 (location-based) | 1.20 |
| Scope 3 (included sources) | 18.00 |
| Total emissions | 19.20 |
| Scope | What it covers | 2024/25 | 2025/26 |
|---|---|---|---|
| Scope 1 | No gas supply at our offices and no company-owned vehicles. | 0.00 | 0.00 |
| Scope 2 | Electricity used at our offices (location-based). | 1.20 | 1.10 |
| Scope 3 | Staff travel between care visits, other business travel, staff commuting, office waste, purchased goods and services, and other operational activities. | 18.00 | 17.00 |
| Scope 3: category 4upstream transportation and distribution | Excluded as not material: occasional deliveries of personal protective equipment and office supplies made by our suppliers' own carriers. We hold no data on these journeys, so each year we will ask our main suppliers for delivery data and include it if it proves material. | Not reported | |
| Scope 3: category 9downstream transportation and distribution | Not applicable: we deliver care in person and do not make, sell or transport products. | 0.00 | 0.00 |
All figures in tonnes of carbon dioxide equivalent (tCO2e).
Reporting year: 2025/26 (1 October 2025 to 30 September 2026, our financial year)
Total emissions were 18.10 tCO2e, 1.10 tCO2e (5.7%) below our 2024/25 baseline.
Our current reporting year is 2025/26, the 12 months to 30 September 2026. We will report each year against the baseline, updating this plan within 6 months of our financial year end.
| Emissions | Total (tCO2e) | Change from 2024/25 |
|---|---|---|
| Scope 1 | 0.00 | 0.00 |
| Scope 2 (location-based) | 1.10 | −0.10 |
| Scope 3 (included sources) | 17.00 | −1.00 |
| Total emissions | 18.10 | −1.10 |
In order to continue our progress to achieving net zero, we have adopted the following carbon reduction targets. We project that carbon emissions will decrease over the next five years to 13.44 tCO2e by 2031. This is a reduction of 30%.
Alongside this, we have set the following targets against our 2024/25 baseline
10% fewer miles driven per visit by March 2028 and 15% fewer by March 2031, through area-based rotas and walking or buses for nearby visits.
A 50% reduction in total emissions by 2034/35 (to 9.6 tCO2e), and net zero by 2045.
Our 2030/31 figure puts us on a straight path from our 2024/25 baseline to a 50% reduction by 2034/35. Travel between visits is the largest part of our footprint, so cutting miles per visit is our main lever.
A note on growth. If we deliver more care, our total emissions may rise even as each visit becomes cleaner; we will explain any such change when we report each year.
| Milestone | Target | tCO2e |
|---|---|---|
| 2024/25 | Baseline | 19.20 |
| 2025/26 | Current reporting year (actual) | 18.10 |
| 2030/31 | Five-year target | 13.44 |
| 2034/35 | 50% below the 2024/25 baseline | 9.60 |
| 2045 | Net zero | 0.00 |
Sustainable Supplier Assessment completed, aiming for Level 1, then renewed each year.
Against our 2024/25 baseline, measured from Birdie mileage and visit records.
Through area-based rotas and walking or buses for nearby visits.
Our five-year target: 30% below our 2024/25 baseline.
A 50% reduction in total emissions against our baseline.
Five years ahead of the 2050 national target.
What we already do, what we commit to on NHS and public contracts, and what comes next.
The following environmental management measures were in place during our 2025/26 reporting year, and will be in effect when performing the contract.
Our care system, Birdie, groups each care worker's visits by area, so that driving between visits is kept short.
GPS check-in on Birdie records where and when each visit takes place.
Care plans, visit notes and medication records are held on Birdie rather than on paper, cutting paper use.
Many of our visits are close together, so our care workers often walk or take the bus between them.
Our office team walks to work.


Area-based rotas, and walking or public transport for nearby visits, for every package of care.
When a person we support needs to travel, we will look first at public transport, community transport and travel training, choosing the most sustainable option that meets their needs.
For team meetings, training and professional meetings where suitable. Care visits and observed practice stay in person.
Each year, using government conversion factors, as part of our social value commitments for its Support in the Community Framework.
In the future we will implement the following measures.
10% by March 2028 and 15% by March 2031 against our 2024/25 baseline, measured from Birdie mileage and visit records.
Completed by 31 March 2027, aiming for Level 1, and renewed each year.
A short session at induction and in the annual refresher, covering travel, energy use and waste.
Our Registered Manager owns this plan, reviews progress every quarter and updates it within 6 months of each financial year end.
Recycling office waste separately, alongside avoiding unnecessary packaging when we buy.
Accountability
Each area has a planned action and a measure we review, so progress is tracked rather than assumed.
| Area | Planned action | How we monitor it |
|---|---|---|
| Travel between care visits | Plan rotas by area on Birdie, order visits to keep journeys short and use walking or buses for nearby visits, without affecting continuity, punctuality or people's choices. | Miles per visit from Birdie and mileage records, reviewed every quarter. |
| Digital working | Keep care plans, visit notes and medication records on Birdie and share documents securely, so that we print as little as possible. | Paper purchases reviewed each year. |
| Office energy | Switch off unused equipment, use energy-saving settings, and choose energy-efficient replacements when equipment is renewed. | Electricity use from our bills, reviewed each year. |
| Staff commuting | Encourage walking and buses where practical, and ask staff about how they travel to work. | Staff travel feedback, reviewed each year. |
| Waste and buying | Avoid unnecessary packaging, recycle office waste separately and consider suppliers' environmental practice when we buy. | Waste and recycling arrangements reviewed each year. |
| Oversight | Our Registered Manager, as environmental lead, reviews progress every quarter and records what has improved and what has held us back. | Plan updated within 6 months of each financial year end and signed off by our Director. |
PPN 006 Carbon Reduction Plan Technical Standard, the GHG Protocol Corporate Standard and the Corporate Value Chain (Scope 3) Standard.
Operational control, UK operations. All figures are in tonnes of carbon dioxide equivalent (tCO2e).
UK Government GHG Conversion Factors for Company Reporting for the relevant year.
Care workers' travel between visits, for which we pay mileage, is business travel (Scope 3, category 6).
Reported on the location-based method.
Well-to-tank emissions and electricity transmission and distribution losses.
We update this plan within 6 months of each financial year end, and earlier plans stay on our website.
Living Plus Care Services Limited
Registered in England and Wales, company number 12901847
Registered office: 32 Market Place, Hatfield, AL10 0LN
Frequently Asked Questions
If your question is not answered here, email info@livingpluscare.co.uk or call 01707 707599.
Chat with our team.The full 8-page plan for 2025/26, signed by our Director on 16 November 2026. Use it in tender submissions, supplier assessments and contract reviews.